Holbeck refurbishment & new build

Click on the relevant Pack below to view

  • Site plans
  • Scheme overview
  • New build elevations
  • Landscape plans
  • House and street scene images

  • Property numbers and accommodation types

Holbeck Project Pack_Refurbishment

Holbeck Project Pack_New Build

Meynell Heights – Front Elevation – Coloured

Meynell Heights – Front Elevation – Lower detail

Meynell Heights – South Elevation – Coloured

  

Refurbishment

Meynell Heights
Block in programme  Dates
Meynell Heights  Internal work from 12th May 2014 until 31st Oct 2015, followed by landscaping to communal areas completed by February 2015
Meynells, Ninevehs & Gaitskells – East Holbeck Low Rise
Streets in programme Dates
Meynell Approach, Square, Walk Scheme starts from 5th Jan 2015 until 20th Aug 2015  followed by landscaping to communal areas completed by December 2015
 
Nineveh Gardens
 
Gaitskell Walk
 Holbeck Back to Back Terraces
Streets in programme Dates
6 Cleveleys Avenue Scheme starts from 5th Jan 2015 until 8th July 2015
8 Colenso Grove
17 Colenso Mount, 7 Colenso Place
1 Colenso Terrace
Rydall Place
Rydall Street
Rydall Terrace
10 and 12 Shafton Lane
Shafton View
1 Tilbury Grove
Tilbury Mount
Tilbury Road
24 Tilbury Terrace
Ingram Court – Sheltered Housing
Block in programme Dates
Ingram Court 7th April 2014 to 9th January 2015
Ingrams – West Holbeck Low Rise
Streets in preogramme Dates
Cross Ingram Road Scheme starts from 20th July 2015 to 9th April 2016
Ingram Close
Ingram Gardens
Ingram Gardens Community Centre
Ingram Road
Shafton Lane (except No. 10 & 12)
28 Willoughby Terrace
Balms West Holbeck Low Rise
Streets in programme Dates
Balm Place Scheme starts from 28th Sept 2015 to 9th Feb 2016
Balm Walk

New Build

Holbeck Moor Road – New Build
Streets in programme Construction Start Dates
Holbeck Moor Road Scheme starts from 11th July 2014 to 18th Dec 2015